The following sequence of images does not show all loading blocks in SAGE-CRISP. Load blocks in which only consolidation time is applied are not shown.
Stage 1 Excavate LHS Pilot (5hrs), also apply free drainage at top ground surface
Stage 2 Shotcrete LHS Pilot (4hrs), followed by 2 week consolidation
Stage 3 Excavate RHS Pilot (5hrs)
Stage 4 Shotcrete RHS Pilot (4hrs) followed by 8 week consolidation
Stage 5 Excavate LHS station tunnel (6hrs)
Stage 6 Shotcrete LHS station tunnel (4hrs) followed by 40 days consolidation
Stage 7 Excavate RHS station tunnel (6hrs)
Stage 8 Shotcrete RHS station tunnel (4hrs) followed by 40 days consolidation
Stage 9 Apply permanent lining LHS tunnel (3hrs) followed by 40 days consolidation
Stage 10 Apply permanent lining RHS tunnel (3hrs) followed by 40 days consolidation
Stage 11 Excavate crown of concourse tunnel (4hrs)
Stage 12 Shotcrete of crown of concourse tunnel (2.5hrs) followed by 6 days consolidation
Stage 13 Excavate bench and invert of concourse tunnel (6hrs)
Stage 14 Shotcrete bench and invert of concourse tunnel (4hrs), followed by 3 months consolidation
Stage 15 Construct inner lining of concourse tunnel, followed by 50 years consolidation
Stage 16 Simulate degrading of shotcrete followed by another 50 years consolidation